Index of /wp-content/cache/flying-press/www.sisinternational.com/ja/検索/if a project network diagram has 4 paths of lengths equal to 10, 13, 15, and 17 weeks, what is the shortest time to finish the project?group of answer choices10 weeks17 weeks15 weeks13 weeks